AKKUYU NUCLEAR POWER PLANT TRANSPORTATIONS
Start Date: 24.09.2020
Date of Completion: 27.09.2020
Equipment used in the project: 2 heavy haulage trucks and 18 axle conventional hydraulic trailers
Project Description: Hareket continues unloading and trasportation of heavy items of the Akkuyu Nuclear Power Plant. After transporting two core catchers successfully, 4 pieces of steam generators, each weighing 360 tons were loaded off the ship and transported to a stock area where they will rest untill the construction of reactor building finishes. Steam generators are the heaviest equipments of the nuclear power plant and were trasported using 2 heavy haulage trucks and 18 axle hydraulic trailers.