Çaypınar Wind Farm
Start Date: 25.09.2020
Date of Completion: 03.12.2020
Equipment used in the project: 600 tons capacity Terex - Demag CC2800 NT Crawler Crane
Project Description: Installation of 7 Vestas V136 wind turbines in Balıkesir Çaypınar Wind Farm has been completed successfully. The turbines has a hub height of 82 meters, rotor diameter of 136 meters and capacity of 3,45 MW’s.