Çimtaş Osmangazi Project

Starting Date: 10.2013
Ending Date: 12.2014

Equipments Used in the Project    : 1 no LG 1750 (750t Lattice Boom A/T Crane), 1 no CC 2800 (600t. Crawler Crane)
24 axles Goldhofer SPMT, 2 unit Power Pack Uni

Project Details:Hareket made pre-assembly works for bridge's leg sections at Cimtas Yard. The sections fabricated horizontally and were taken out of factory by SPMT's. Each section were upended at the yard and got trial assembled onto each other. Consecutively, Hareket loaded the sections onto SPMT and made the transportation from Yard to Port (app 4kms). The bridge has 4 legs coynsisting of 16 sections each, total of 64 sections. The heaviest section -section 1's- was 11m by 9m, weighed 320 tons.