What are you looking for?

Gama-Hamitabat - Hamitabat Natural Gas Combined Cycle Power Plant

Starting Date : 04/04/2016
Ending Date: 06/30/2016
Equipments Used in the Project: Two 20 axles with 240 wheels, 1,5 Goldhofer hydraulic trailer, eight tow trucks, one 220 ton capacity Faun ATF 220 G-5 and one 120 ton capacity Liebherr LTM 1120 mobile crane, four auxiliary trailers (one 15 axles Goldhofer Hydraulic trailer, two flatbeds, one 7 axle lowbed) were used.
Project Details: Two 480 tonner natural gas turbine, two 450 tonner generator and thirty 180 to 220 tons of HRSG modules were transported.