What are you looking for?

Kipaş Paper Transportation and Installation Project

Start Date : 01.09.2019
Date of Completion: 05.09.2019
Equipment used in the project: 16 axle hydraulic semi-trailer
Project Description: The transportation of 110 tons of drying equipment to be used in Kipaş Paper Factory in Aydın Söke Organized Industrial Zone was carried out by Hareket. Drum Pulper, the production of which is made in China, was lowered on to 16-axle Goldhofer hydraulic trailer in Izmir Aliağa Nemport port. The installation of the 35 meter long load was completed with a 400 ton capacity Gantry. The equipment was lifted and mounted on a 5.3 meter high base with HSP 1000 Spindle Jack Gantry.